Union Cabinet has approved establishment and operationalistion of permanent campuses of the two new Indian Institutes of Science Education & Research (IISERs) at Tirupati (Andhra Pradesh) and Berhampur (Odisha). The total cost likely to be incurred is Rs. 3074.12 crore (Non-Recurring: Rs.2366.48 crore and Recurring: 707.64 crore).
Creation of two posts of Registrar, one in each IISER in Level 14 of 7lh CPC has also been approved by the Cabinet.
Details:
- The total cost is assessed at Rs. 3074.12 crore, out of which 2366.48 crore will be spent for construction of permanent campuses of these institutes, as per the following details:
Institutes
|
Capital
|
Recurring
|
Total
|
IISER Tirupati
|
1137.16
|
354.18
|
1491.34
|
IISER Berhampur
|
1229.32
|
353.46
|
1582.78
|
Grand Total
|
2366.48
|
707.64
|
3074.12
|
- Both the IISERs will construct an area of 1,17,000 sq. m which will have complete infrastructural facilities for 1855 students in each IISER.
- The construction of permanent campuses of these institutes shall be completed by December, 2021.
Benefits:
The IISERs will provide top quality science education at the Under-Graduate and Post-Graduate levels, PHDs & Integrated PHDs. They will carry out research in frontier areas of science. They will enable India move towards being a knowledge economy by attracting the best scientific talent as faculty and prepare a strong base of scientific manpower in India.